|
Section 48.13 Block 1 Lot 6 August 18, 2008 Request 2nd 90 Day Time Extension & Request for Development Sign Location: Underhill Avenue, Yorktown Heights Contact: Al Capellini, Project Attorney Description: 5-lot subdivision approved by Planning Board Resolution #07-23 dated October 15, 2007. The Planning Board approved the sign for the development since it met all town sign regulations. The extension, necessitated by delays in dealing with NYCDEP and the County Health Department, was granted. October 6, 2008 Request for reapproval: This reapproval, necessitated by delays in getting Board of Health approval, was granted. Currently the DEP is considering the stormwater and pollution control plan.
January 12, 2009 work session January 26, 2009, Special Session Mr. O'Keefe asked the Planning Board to grant the necessary town wetland and excavation permits at this time, even though the project has not yet received its DEP permit. Supposedly the DEP permit has been conceptually approved, but not actually received. Mr. O'Keefe is in a position where he needs to be able to accept excavated material from another project on a moment's notice and therefore wants to expedite the permitting process. The Planning Board was reluctant to grant town permits without knowing what the DEP permits will require, because often the DEP has different requirements that have to be subsumed into the town permits. Mr. O'Keefe argued that the town had nothing to lose since he couldn't do anything without the DEP permit anyway. The Planning Board agreed to give the town permits pending the DEP permits, but warned that whatever the DEP required could change the bonding requirements for the project. On the topic of bonding, previous meeting's discussion was resumed. Mr. O'Keefe submitted to the Planning Board and Engineering Department detailed plans for the sequencing of the project. Based on this the Town Engineer decided a $20,000 bond was necessary for the erosion control portion of the project. Mr. O'Keefe thought $20,000 was excessive. Ms. Steinberg pointed out that the $20,000 figure put out by the town engineer covered only erosion control and additional amounts would be necessary to guarantee the wetland mitigation work. Mr. O'Keefe argued that only phase I had any wetlands encroachment so the amount of the bond should be based only on that phase, not the cost of the whole project. Also he maintained the bond should be returned after phase I was completed. Mr. Klaus informed Mr. O'Keefe that wetland mitigation bonds are the town's standard operating procedure and are kept for several years to insure that the mitigation works as designed, is maintained and the new plants survive. Finally, Ms. Steinberg suggested that Mr. O'Keefe submit cost estimates for each phase and that they meet to arrive at an appropriate bond amount. Mr. O'Keefe was agreeable to that. February 9, 2009 The board approved the request for both an excavation and wetlands permit after the developer worked out the details for both the erosion and wetlands bonds with the town engineer. The erosion bond will be for phases. Phase I will consist of bringing in fill and creating the stormwater retention pond. The bond for the wetlands permit will cover $4,000 worth of new plantings and the labor to install them and will remain in force for three years, which, according to Mr. Klaus, was the typical period of time needed to establish the fact that at least 80% of the plantings have survived.
April 13, 2009 The Planning Board approved a request for the 1st 90 Day Time Extension for this 5-lot subdivision approved by Resolution 07-23 dated October 15, 2007 and reapproved by Resolution 08-22 dated October 6, 2008. Progress is expected on the site with the onset of warmer weather. June 8, 2009 Request for 2nd 90 Day Time Extension. The applicant is continuing to make progress on road construction into the proposed subdivision. The Planning Board granted the requested extension. October 5, 2009 This is a request for reapproval. The work on this site is continuing slowing. Mr. Tegeder said he received frequent environmental reports, and there have been no problems/violations. Mr. Capellini pointed out that this project is under the supervision of the DEC, DEP and Department of Health because it is on a steep slope, above a stream which empties into the Croton Reservoir. He said that even in this very rainy summer, there have no erosion problems. The Planning Board voted to reapprove the project. |