|
Aspen & Mill Street Subdivision
November 24, 2008, work session March 23, 2009, work session July 13, 2009, work session The board then proceeded to review a subdivision plan that would include two additional lots that would conform to the proposed one acre zoning for the site. Most of the discussion centered on the FEMA designated floodway and floodplain areas on the map. While the site plan called for the new lots to come off an existing common driveway, Mr. Flynn suggested that as long as the property owner was going to make a profit, that the plan be done the 'right” way and that the driveway be relocated in order to take it out of the existing wetlands buffer. In response, Mr. Capellini noted that by constructing a new road there would be more disturbance to the site. Mr. Riina agreed that the proposed driveway for one lot could be flipped so that the same general area could be constructed along the same path planned for the utility lines. As the site has serious environmental constraints, it was suggested that the applicant run the plan by both the Conservation Board and the town engineer and Mr. Klaus advised the applicant that he was proceeding at his own risk on a plan in doing any additional planning on the site. |
|
November 23, 2009, work session Mr. Riina described how the driveway to the new lots has been moved out of the wetland and the original driveway area will be returned to a natural state. While excavating for the new driveway, a larger storm water basin will be installed. Ms. Kutter, Conservation Board liaison, asked about the location of the conservation easement, but this has not yet been determined. Mr. Flynn commented that the plan “looks viable”, except for the non-conforming use issue.
There was considerable discussion about the intensity of use on the site, given the two existing residences. Mr. Flynn disagrees with the ZBA’s ruling that the existing, non-conforming structures do not increase the intensity of use on the site and that only an “area” variance is required. He thinks the intensity of use is increased, and his independent research on the case law suggests that increased intensity of use issues should be strictly interpreted. He had asked Planning Board Attorney Wagner to research the case law, but Mr. Flynn hadn’t yet had a chance to read the results. Mr. Flynn said a Public Information Hearing would not be scheduled until this issue was resolved to the Planning Board’s satisfaction. The applicant’s attorney, Mr. Capellini, was clearly annoyed by this delay, pointing out that the ZBA had granted the necessary variance and reminding Mr. Flynn of his own experience on the ZBA. He also said the other cases Mr. Flynn referenced were not on point. Ms. Wagner said the intensity of use issue was within the purview of the Planning Board and the Board was within its rights to delay action until the issue was resolved. The issues of non-conforming uses and intensity of use will be discussed at the December 14, 2009 meeting. |
|
December 14, 2009, work
session Mr. Riina described how one driveway had been moved and that the area between the brook and the driveway would have a conservation easement. It will be reforested and serve as a flood control area. This is the wetland mitigation area. Ms. Steinberg asked that the wetland permit application be amended in light of the driveway relocation. There is a long-existing parking lot in the wetland buffer area. The Conservation Board did not address this in its comments. Mr. Klaus questioned the sight distance
on There was no discussion of the variance granted by the ZBA. A Public Information Meeting was scheduled for January 11, 2010 |
|
January 11, 2010, regular session Public Informational Hearing Mr. Capellini summarized the site’s zoning issues. The site is 5.6 ac. in an R1-20 zone. It currently has a 9 family house and a one family house on it. The proposal is to subdivide the property into four lots, with each of the existing structures having its own lot, and building two new single family houses on the remaining two lots. Each of the proposed lots would be over 1 ac., well within the current zoning regulations and also within the 1 ac. zoning proposed in the Comprehensive Plan. The existing structures are non-conforming for two reasons: (1) a multi-family dwelling in a R1 zone and (2) two dwellings on one lot. The ZBA ruled that the non-conformity was in the use of the multi-family building and that the proposed subdivision would not increase the extent of non-conforming use.
Mr. Riina described the physical layout of the site. One new dwelling will have its driveway
open onto
Mr. Flynn questioned whether it is correct to include the portion of the lots within the flood plain in calculating lot size. Mr. Riina and Mr. Capellini maintained their lot size calculations are correct, but would verify the issue of including flood plain acreage.
Mr. Flynn pointed out that Mr. Capellini had used an example of an R3 zone in his arguments before the ZBA. Mr. Flynn maintained that if the proposed subdivision is parallel to a R3 situation, as Mr. Capellini argued, then R3 standards should be used in its approval process. This would require 400 sq ft of open space per unit and a 1200 sq ft playground. Mr. Capellini maintained this would be inappropriate because (1) the uses of the property are legal, if non-conforming, (2) the zoning is R1-20, not R3 and (3) he used the R3 zone merely as an example before the ZBA. No other Planning Board member spoke on this issue. No conclusion was reached on which standards the Planning Board would require.
There were no questions from the public, and the Public Information Hearing was closed. |
The Building Inspector had been asked to interpret the term “periodic flooding” and the implications for building under such conditions, but declined to comment on the basis that even if the portion of the lot in the flood zone is subtracted, there still is enough buildable area on the lot. Mr. Riina described how the parking for the multifamily dwelling will be moved from several small areas adjacent to the stream and concentrated into one large lot near the building. All the run-off from the paved surfaces will be captured and treated, but the total amount of impervious surface still needs to be quantified and the storm water management plan needs to be documented. The plan is to reclaim the original parking area and make a park-like setting up to the brook. There will be a conservation easement along the driveway and brook wall. Mr. Tegeder questioned whether it is appropriate to consider planting in the wetland buffer as wetland mitigation. The wetland mitigation plan still needs to be formalized. A public hearing was set for May 10, 2010.
Return to Home