October 6, 2009
Public hearing/Wetlands Permit for Patriot Garden
Planning Director John Tegeder explained that the project dates back 5-6 years ago and that the town had gotten a $78,000 grant from the NYS Parks Dept for a portion of the project which will be a semi formal garden where people could sit and have lunch. Councilman Bianco explained that the project is basically changing plants replacing the invasive species that are there now with a new mix of plantings. The project will also strengthen the wetlands buffer areas and provide additional treatment to stormwater coming from the adjacent parking lot.
Mr. Tegeder had seen the memo from the Conservation Board and said there were no problems.
In response to Vishnu Patel's question as to who would maintain the garden, Councilman Lou Campisi said that the maintenance question was not relevant in a hearing for a wetlands permit
Howard Frank had a question about what he called a snow fence on the plan, but Mr. Tegeder explained that this was probably a temporary silt fence that would be removed after construction.
The hearing was closed and the board approved the wetlands permit.
Jefferson Valley Sidewalks Project
January 27, 2009, Town Board work session
Although not on the published agenda, there was a brief discussion about the need for an additional $11,000 for the previously approved Jefferson Valley Sidewalk project. The board will vote to authorize the additional funds at its Feb 3rd meeting. (Although not explained so that those in the audience could clearly hear, it seemed that the need for the additional funds was because the bids for the job came in higher than anticipated.)
February 3, 2009
Jefferson Valley Sidewalks
The board approved a resolution authorizing an additional $11,704 in town funds for a total town contribution of $129,304 for the cost of installing sidewalks along East Main St in the Jefferson Valley hamlet. The town's contribution covers 32.7% of the project cost; the remaining funds are coming from the CDBG program.
The board also awarded a bid for the construction of the sidewalks.
Sidewalk construction on E. Main St in Jefferson Valley
July 7, 2009
During Courtesy of the Floor, Greg Bernard and Linda Clemenza both asked the board to look into problems associated with the sidewalk construction on East Main Street in Jefferson Valley. They noted that signage did not provide adequate warning notice for drivers. They also questionee the placement of unlit barrels in the road that could be dangerous for drivers at night not familiar with the road.
The owner of Osceola Beach who hosted the board's meeting, also talked about problems associated with the construction.
In response, Highway Superintendent Eric DiBartolo said that both he and Planning Director John Tegeder had spoken to the private construction company doing the work and that they will try to improve conditions.
In response to a question from Gil Kaufman about the cost of the sidewalks, it was explained that 70% of the money was coming from Community Development Block Grant money and 30% from the town. The board approved an additional $16,962 for the project with the funds coming from the town.
July 21, 2009
Additional payment for Jefferson Valley Streetscape project
The board approved a resolution authorizing an additional $9,497 for the Jefferson Valley Streetscape Project.
Jefferson Valley Sidewalks/Valley Market
July 14, 2009, work session
Planning Director John Tegeder reviewed preliminary plans to realign the parking area in front of Valley Market on East Main St. as part of the area's sidewalk program. Six of the 14 accidents in the general area have involved the market because there is no clear ingress or egress and cars back out onto East Main St. A portion of the parking lot is actually in the town's right of way. The proposed plan calls for angle parking with an ingress and egress. The owner objects to the plan which he says will kill his business.
Councilman Matt Metz said he doubted the doom and gloom scenario and Highway Superintendent Eric Di Bartolo said the new plan made sense. He suggested that as an experiment, the town might install temporary barriers to simulate the proposed changes to see how the plan might work.
Attorney Al Capellini, representing the owner of the market, said that his client had hired his own engineer to come up with an alternative plan and he asked the board not to proceed with the town's plan until the engineer submitted his ideas. Mr. Tegeder said that the town could wait about two weeks before proceeding so the issue will likely be discussed again at the board's August 28th work session. Councilman Metz suggested that Mr. Capellini try to get the engineer's report to the county before August 28th so that it could complete its review prior to the meeting.
July 28, 2009, work session
The board resumed the discussion of the traffic control plans in front of the Jefferson Valley Market. Planning Director John Tegeder showed a revised plan that would channelize and control traffic into and out of the site but the owner of the market and his engineer continued to object to the plan on the grounds that it would hurt his business, particularly from truck drivers. Highway Superintendent Eric DiBartolo also objected to the proposed island and angle parking which he said could cause a stacking up of cars on East Main Street.
All agreed that the first priority should be safety, followed by upgrading the aesthetics of the area.
Various alternative solutions were discussed including the possibility of reducing the height of the island to replacing the island with a concrete apron that would look like a sidewalk and be level with the road, to painting a pedestrian walkway across the road.
In the end, the board advised the planning department to meet with the owner and the county engineer working on the project to arrive at a compromise plan.
October 13, 2009, work session
Jefferson Valley sidewalks/Wood St & East Main St. intersection
Planning Director John Tegeder asked the board for approval for an additional $44,740 to re-grade and pave the intersection of Wood St and East Main Street in order to make the intersection safer. He said that both the highway superintendent and the town engineer supported the new design over the original plan. He suggested that the money come from the funds that the county gave Yorktown when the town took over East Main St as part of the legacy ballfields project. No one was quite sure how much money was remaining in that fund as Mr. Tegeder's figure pre-dated the recent paving work that had been done.
The board passed the resolution approving the use of the funds. If the county road fund does not have the money, Mr. Tegeder said he would need to come back to the board.
Return to Home Page