Directory
DEC: New York State Department of Environmental Conservation
NYSDOT: New York State Department of Transportation
SEQRA: State Environmental Quality Review Act)
Tegeder, John: Yorktown Town Planner
Klaus, David: Chairman, Planning Board
Flynn, John: Planning Board member



Crompond Corners

Section 26.18 Block 1 Lot 7
Location: Old Crompond Rd. and the Bear Mountain Extension, Yorktown Heights, across from the BJ's complex, behind the old Midway Hardware building
Represented by: John Sullivan, project architect and Carl Ackerman
Description: 28 proposed senior housing units and approximately 14,000 sq. ft of proposed one story retail/commercial

Planning Board Work Session, February 11, 2008
Pre-preliminary application

This project will require a re-zoning to RSP2 (mixed use, commercial and residential). The Master Plan calls for this change, but it has not yet taken place. The Town Board is expected to act on it in April or May. Mr. Tegeder said the application could be processed contingent on the rezoning. The applicant recognizes the gamble in investing too much in the project, absent the required rezoning. At this point, the applicant is looking for the Planning Board's comments on conceptual plans. No engineering has been done.

The proposal calls for 14,000 sq ft of commercial/retail space in two buildings fronting Old Crompond Rd. The exact configuration of the buildings would depend on the types of businesses they attract. Parking will be in the back of the buildings so as to avoid a strip mall appearance. Twenty eight townhouse-type dwellings will be built behind the commercial area. They will be a mix of eight 1-bedroom and twenty 2-bedroom, age-oriented (55+) units, owned as condominiums. The condos will sell for $350,000 to $450,000. It is expected that most of the units will end up being sold to people who already live in Yorktown.

The architect is emphasizing “New Urbanism” in his design. This includes a “streetscape” design with sidewalks, parallel parking rather than angle parking, commercial parking behind the businesses and garages opening on the sides rather than the fronts of the residences. Walking to the BJs/Staples complex is thought to be an advantage, although there is some concern about exactly how pedestrians will cross route 202.

Mr. Sullivan said they were looking into the possibility of connecting this site to the proposed commercial space at the old Yorktown Motor Lodge site via Old Crompond Rd. The Planning Board asked the applicant to consider a connection to the walking trails in the Deer Hollow subdivision on the other side of the Bear Mountain Extension. Again the question of safe pedestrian crossing of a busy highway was brought up.

There are extensive wetlands on the site, but the applicant does not plan any activity in the wetland or its buffer area, not even the storm water detention system.

Mr. Flynn asked whether the two bedroom units would attract families with children. Mr. Sullivan said that even retired, empty-nesters demand two bedrooms and that there is little market for one bedroom units.

The Planning Board was very positive about this conceptual plan, commenting that it is “what we like to see”. The Board told the applicant that the next step is to look at environmental issues, including delineating the wetland and designing storm water management systems.

Mr. Klaus commented that due to market conditions, the Planning Board is seeing more and more of this type of small project, rather than large, multi-lot subdivisions. This suggests a change in the pattern of the Town's future growth and development.


November 24, 2008, work session
The applicant returned to the planning board with a slightly revised preliminary plan for additional board review and guidance.

One of the six proposed residential building has been eliminated, leaving the number of planned dwelling units at 26. The units, one and two bedroom, will range from 1,000-1,800 sq. ft. The applicant plans to enter into discussions with the county regarding making the smaller, one bedroom units available as affordable units.

The board asked the applicant to confer with the adjoining JP Morgan Chase Bank so that the development of the two sites could be coordinated, especially regarding sidewalks and other pedestrian friendly aspects of the plan. (See summary of JP Morgan Chase Bank.) Of particular concern is the traffic situation at the Stony St/Bear Mountain Parkway intersection. Mr. Giordano noted that while the 26 residents units would not generate much traffic, the stores would have to attract additional shoppers in order to be viable.

The two commercial buildings are being planned to attract small service oriented uses and although each building will be a single unit, the use of different design elements will make each store within the single building look like a separate attached building and not a typical strip center. The rear of the buildings will also be attractively designed.

In general, the board was supportive of the plan which it felt was a good use of the site. They also felt that there was a need for more moderately priced age oriented housing in town.

In addition to the traffic issue, the board will be taking a close look at the site's environmental issues, including delineating the wetlands and protection of the Hunterbrook stream. Mr. Klaus noted that the existing pool on the site (which will be demolished) dates back about 40 years and was built by the DEC as a trout stocking pool. The pool is fed by the stream.

The rezoning to RSP2 is still contingent on the adoption of the revised Comprehensive Plan which has not been done yet.


February 10, 2009, town board work session
The applicant, Sammy El Jamal, made a brief presentation of the mixed use residential-commercial development. (for details about the plan, see the previous highlights of planning board meetings.) The issue under discussion was the status of the master plan revisions as the site plan is based on the new RSP2 zone that was put in place in 2005 but rescinded after some property owners challenged the new master plan in court and won. Hearings on the revised master plan are scheduled to take place soon, but no dates have been set. Planning Director John Tegeder told the applicant that he wasn't aware of any changes that were contemplated for their site in the revised plan and he advised them to proceed with their plans. Walter Daniels of the Conservation Board said that his group had some issues with the site as portions of it were located in a flood plain.


August 10, 2009, work session
Discussion Site Plan & Residential Site Plan
The applicant prefaced comments with the proviso that the whole project depends on the site being rezoned as called for in the comprehensive master plan.  The plans call for commercial development in the front along Old Crompond Rd and age oriented housing in the rear, which is perfectly compatible with the proposed rezoning.  The applicant feels that the project is a good match for the site and that the site can support their proposal.  In fact the applicant feels the site is being improved since the landscaping plan makes use of areas that are already disturbed.  For example, the retention areas will replace an old pool area, specimen plants and rock outcroppings will be preserved and incorporated into the landscaping.  Mr. Klaus pointed out that protection and improvement of Hunter Brook is a major Planning Board concern, and that additional wetland mitigation might be required. 
 
Traffic, engineering and landscaping plans have all been completed, and the applicant urges the Planning Board to review them.  The installation of water and sewer lines will be straightforward with the project connecting to a sewer line on rte 202.
 
CAB liaison Ann Kutter asked if bike racks would in included.  Mr. Sullivan said they would be considered, but didn't think the area was very conducive to biking.
 
Mr. Tegeder asked about affordability of the housing units.  Mr. DeLuca said that hadn't been decided yet, but the housing would be for homeowners over 55.
 
Mr. Sullivan described the commercial building as being pedestrian friendly with landscaping and possibly outdoor restaurant seating in the front and parking in the back.  Mr. Tegeder disagreed with Mr. Sullivan about the street friendliness of the faade, suggesting that landscaping of the type proposed often tends to close off access, rather than open it up.
 
Ms. Kutter asked if the buildings would be LEED certified (=Leadership in Energy and Environmental Design).   Mr. Sullivan said they would be green and very energy conservative, but not necessarily LEED certified.
 
There was extensive discussion about what could be done on this project while waiting for rezoning, including the role of the Planning Board in urging the Town Board toward that action.  The applicants asked if the Planning Board ever commented to the Town Board on a specific rezoning and suggested the project could benefit by spotlighting by the planners.  The applicant suggested the Town Board could be catalyzed to rezone the property if it was made aware that there is a project suitable for the site and all ready to go.  Mr. Klaus said this is a nice, little concept and that the town doesn't have anything along these lines.  Yorktown Commons was supposed to be commercial space on the ground floor with residential upstairs, but the commercial space has given way to professional offices.  The applicant asked what the Planning Board could legally do before the rezoning.  Mr. Klaus said the Planning Board could review all the technicalities of the project in order to be ready to vote once rezoning happens.  Ms. Wagner said she would have to research the issue of having a public informational hearing and public hearing before the rezoning.  Mr. Tegeder said that under previous building moratoria, projects were processed as if the project met the proposed zoning changes, but at the applicants risk.  Mr. Giordano suggested the applicant enlist the support of the Chamber of Commerce to lobby the Town Board toward rezoning.
 
Ms. Steinberg advised the applicant to submit its wetland permit application so the mitigation plan could be reviewed and the wetland flagging verified by Bruce Barber, the towns environmental consultant.  Mr. Klaus concluded that environmental issues will be the biggest concern for this project.