Director of Labor Operations
(Water, Highway, Parks Maintenance, Sewers, Maintenance of Town Buildings and Environmental Conservation)



This page is divided into the following sections, although because of the overlapping nature of some of the items, it is not always possible to segreate every topic into its own section.
Reorganization of departments
Water Department
Miscellaneous issues (parks, YCC, staff allocation, etc.)
Energy conservation related issues
Fleet Committee (town vehicles)

 

Reorganization of Departments


Background information
At November 17th meeting to review proposed 2008 budget, the board announced that it was planning to create a Department of Public Works that would be separate from the Highway Department and that the current highway superintendent would simultaneously head both departments. The DPW would put the Water Department, Environmental Conservation and Parks in a single department.

11/27/2007 (work session)
1. board made changes in text of proposed local law setting up the DPW and an accompanying resolution
2. during the meeting, on two separate occasions, Roker leaned over to a councilman and whispered something that was not explained to the public
3. Metz and DiBartolo confirmed that what they were doing was permitted by the Attorney General's opinion that had been cited at the earlier November meeting.
4. Metz said that the key was making it legal to consolidate the departments and having the highway department fall under the DPW.
5. more than once it was said that to get rid of the highway superintendent there would have to be a referendum. They didn't explain if they meant getting rid of the position entirely or changing it from elected to appointed.
6. Martorano expressed concern that the board wasn't creating a department based on a person or personality; "we'll have to have this once Eric (DiBartolo) leaves. The saw needs to be objective."
7. Metz: after Eric leaves, we can do away with highway superintendent.
8. board never answered question of how DPW head could be under control of town board if he was an elected official.


12/11/2007 (work session)
Deputy town attorney John Buckley (not at the meeting) checked with civil service, title of Supterintendent of Public Works as presently planned won't work so its being recommended to use a "functional title" that is outside of any civil service classification.

Bianco wanted to know when all this surfaced; he seemed surprised and "out of the loop" Metz possibly said, "Today."

Metz basically said that this would allow town to do what it wanted to do, but just with a different title

Roker said town didn't need to create a department which also meant that town could make the change resolution and not local law. Could accomplish same objective by resolution, not local law

Roker said Buckely said the new title should be run by civil service

Bianco questioned what was the meaning of the 12/18 public hearing. Roker said hearing could go forward. She said they'll test this out for 6 months or so and then see if it works and if it does, then they can look into a DPW.

Bianco asked whether this had been researched before.

Board also discussed the hire/fire provision in the law/resolution and someone (Roker?) said that aDiBartolo realized that this power vested with the town board so they'll have to change language of the draft resolution which current would give hire/fire power to the highway superintendent.


12/18/2007 (public hearing)
Roker explained reasons for consolidation. How she had problems in the past getting truck to haul voting machines. Also requests from Parks Dept for additional staff to deal with heavier work load. Talked about how DiBartolo had found Water Department vehicles that could be used by Parks and also other ways to helps Parks handle tasks. Library also needed more maintenance staff. She said town saved $200,000 by eliminating three laboroer positions in 2008 and use of flextime. She praised DiBartolo: "Can't stress enough what he's been doing in Water Dept" – and he has plans for Parks."

Roker also said that DiBartolo was the only one board considered for the position. "Our goal is to save money not spend it." She cited additional costs of having a DPW commissioner. $125,000, plus benefits and secretary.

Roker did acknowlege at least two other salary increases related to the reorganization but she didn't cite the $$ increase for them.

Most people who spoke at the hearing were in favor of the plan and most praised DiBartolo.

The only comments opposed or raising questions came from Susan Siegel, a Ms. Daniels (wife of Walt Daniels of Conservation Board) who questioned the problem of having the new Director of Manpower Operations (which will be changed to Labor Operations make it gender neutral) both elected and appointed. She also said that the elected highway superintendent position should be eliminated and she raised the need for a job description and other civil service issues.

Geri Schwab said that the position should be established first, then a job description developed and then DiBartolo appointed. Roker said the job description was in the resolution.

Roker also said that department heads will control their budgets.

Incoming supervisor DonPeters said DiBartolo was the only one who could do the job. "Basically, I wouldn't be in favor if it wasn't for him. (Martorano and I think Bianco said basically the same thing.)

When questioned on the $200,000 savings, Roker said the figure was from the comproller.

Metz rejected Siegel's statement that the meetings were behind closed doors; he said only personnel was discussed behind closed doors. He also said the plan wasn't hastily prepared and that DiBartolo having masters (i.e., being both elected and appointed) was a plus and a good thing. He said we don't have a crisis, but it's time to act now. "Let's break down walls without creating a DPW. There's no time to study."

Campsi and Roker (and Panio) attacked North County News for the editorial and cartoon. Campisi: they didn't write the truth.

Bianco said the new plan "wasn't about eric"; we would have selected someone else if we could save $200,000. He sees each department as being a separate government and noted that no one lost their job- this was paramount issue for him. It's not perfect – but is not dangerous.

Siegel asked about when the town would send a formal job description to civil service. Roker said she would look into it. She convinced that the resolution will pass muster.

Jeramiah Dineen also raised the elected/appointed issue.

Roker and town attorney said they had been in touch with Westchester Commissioner of Human Resources on the civil service implications of the new title and that the commissioner was okay with it.

Speaking up in favor: Mike Kaplowitz, Rosemarie Panio, Joe Apicella, Dr. Jules Brodsky, a member of Rec Commission, and some others. During the Courtesy of the Floor, the woman in charge of water meters read a glowing statement about what DiBartolo had done for the department.

The resolution passed unanimously.


March 17, 2009
Steve Gardner, speaking at both courtesy of the floor segments, said that the highway superintendent should be focusing his attention on the roads, many of which he said needed work, instead of working on other projects related to the consolidation of labor services. He cited a situation on Baptist Church Road as one such problem. He also said that for people considering running for the job of highway superintendent, it wasn't a level playing field when the current highway superintendent had the additional responsibilities associated with the Director of Labor Operations position.

In response, Councilmen Metz explained that the consolidation of the work force had saved the town money and had enabled the town to take on other projects such as the skate board park and the legacy ballfields. Councilman Campisi said that the consolidation had saved the town over $1 million.


Water Department


Water meters in shopping centers
11/13/2007 (work session)

This was not on the agenda but DiBartolo brought up.
He told board that the town was losing money in its shopping centers because some stores didn't have meters and others were tapping off other lines. He didn't quantify the amount of loss. Joan Goldberg, comptroller, said: “Yes, we've known for a lot of years that this is a problem.” DiBartolo said he was advised of the problem by a meter reader in the department. He said he spoke to town attorney about this although content of discussion was not explained.

DiBartolo suggested that way to correct the situation was to have one meter for the center that landlord would be responsible for and that it was up to landlord to install sub meters for the tenants.

Martorano thanked DiBartolo saying it sounded like a good idea
No decision was made on next steps and/or who would follow through with issue.

11/27/2007 (work session)
1. town attorney said that earlier law talked of master meters but it didn't have a time frame for implementation.
2. town will work on the needed draft law

12/18/2007 (public hearing)

DiBartolo explained that this has been going on for “many many years.” The woman in charge of meters said that when she brought this to attention of her superiors earlier, she was told “to keep quiet.”

DiBartolo implied that the lose of revenue may not have been great but that “nickels and dimes” add up. Said Yorktown was relatively good in terms of not having a large amount of “lost” water usage.

Adam Brodsky, manager for Triangle shopping center said it would be a hardship to put new law into effect as of Jan 1st. He asked for a 5 year phase in. His leases make tenants responsible for paying their water.

Conclusion; board passed the new law, unanimously, but with implementation delayed until April 1st.


1/22/2008 (work session)
1)Updates
a) DiBartolo is proposing to purchase software that will monitor capacity and pressure in existing water tanks which would help town deal with water main breaks, adjustment of chlorine levels and allow pressure in tanks to fluctuate – which was needed. He had a computer and demonstrated how the system would be used. He said he has discussed the software and pressure issue with the Joint Waterworks people "who don't know what they're pumping to us."

Board asked him if "we have the money." He said yes, but the cost was not identified. (At end of meeting, after DiBartolo had discussed other issues with the board, and almost as an afterthought, a board member asked the cost of the system and he said $65,000-$80,000.)

2) Cost of water connection permits
DiBartolo gave board a "heads up" on an issue likely to come before it. A developer applied for several water connection permits in June, 2007 but he never actually paid for the permits at the time. In August, 2007, the board increased the permit cost to $10,000, from $6,000.

The developer recently come to the town to actually pay for the permits and felt he should pay the $6,000 rate, not the $10,000 rate now in force. The water dept. will not issue the connection permit until the developer pays the $10,000 rate.

Now aware of this type of issue, DiBartolo has amended the application for water permits to say that they are only valid if paid for within 72 hours.


April 22, 2008 work session
Director of Labor Operations Eric DiBartolo reported to the board that the Triangle Shopping Center and Kmart were the only two commercial businesses that had not met the April 1st deadline for installing a single water meter on their premises, He said that the manager Triangle Shopping Center was purposely delaying complying with the new law and had ignored two registered letters.

After the board generally agreed that in the face of continued non compliance the town's only recourse was to shut off the water, the discussion focused on how to proceed, especially in a way that would not hurt the tenants in the shopping center.

On the advise of Town Attorney John Buckley, a "demand letter" will be sent the property owners giving them a fixed number of days to comply with the law before water is shut off. Copies of the letter will be sent to the Westchester County Department of Health and to all tenants in the Triangle Shopping Center on the theory that once they realize what could happen to their businesses, they will pressure the landlord to comply with the law. Mr. DiBartolo said that the necessary work could be completed in about 10-12 days. Mr. Buckley said the letter would be sent out, certified, return receipt requested, on April 23rd.

Town Clerk Alice Roker told the board that if it did not take action to force compliance, as a taxpayer in the water district she could sue the town because she would be put in a position of having to pay for someone else's water.

May 6, 2008
A bid was approved for a new pump station that serves 12 homes. (Because the homes are so close to the water tank they cannot get adequate pressure.) The cost will be $35,000 and some of the installation work will be done by town staff. The plans are currently being reviewed by the county Department of Health.

Miscellaneous Water Department information
Mr. DiBartolo told the board that by using new software he had purchased he was able to turn off any water tank as soon as the location of a water main break was identified, thereby eliminating water loss. The software also monitors water levels in each tank and prevents overflows which had occurred in the past.

Three department employees who had been previously been promoted thanked the board for its support of their job performance. They also praised the work of Mr. DiBartolo.

Shopping center water metering
This issue was not discussed in detail but rather by innuendo. It appeared that the town has not been able to get compliance from the two shopping centers who have failed to comply with the new master meter law but that town officials were still trying to work out a resolution of the issue. It appeared that one reason the issue has not been resolved yet might be a disagreement among town board members, but this was not explained – just alluded to in passing comments.

In the meantime, Councilman Campisi asked Mr. DiBartolo to explain the relationship between unpaid water bills and unpaid sewer bills. As sewer bills are based on water usage, it was pointed out that improper water metering also meant a loss of sewer district revenue.


July 1, 2008
The board authorized the sale at auction of a jet vac machine. (Note: Earlier in the meeting, Supervisor Peters noted that the purchase of this piece of equipment would result in a shortfall in the equipment line item budget for 2008. At a previous work session, town comptroller Joan Goldberg advised the board that the equipment could not do the job it was supposed to do and could either be returned to the vendor for a 15% restocking fee or sold at auction.)


July 15, 2008
During Courtesy of the Floor, Howard Frank asked again about the issue of “lost water” and wanted to know what the town was doing to identify those people who weren't paying for water they consumed. In response, Supervisor Don Peters said that the issue was being investigated. Director of Labor Operations DiBartolo said that at the end of the year he would have a report on the measures he had taken to reduce the loss. One measure he has instituted is that when a user has a permit to draw water from a hydrant, the water is now metered and the user pays on the numbers of gallons used instead of a flat fee which was the past practice.


June 3, 2008
During Courtesy of the Floor, Howard Frank noted that the official Annual Drinking Water Report for 2007 for the Yorktown Consolidated Water District stated that the town had “lost” 235,000,000 gallons of water, i.e., that amount of water that had been purchased from the Joint Water Works was not reflected in metered water sales. The loss represented 21% of the total water purchased from the Joint Water Works.

Councilman Bianco noted that the town was trying to cut the loss to 10%. “We're working on it,” he said.


August 19, 2008
Water usage for
Cortlandt residents
During Courtesy of the Floor Howard Frank asked the board how approximately 100 property owners on 34 streets in Cortlandt who receive water from Yorktown through the Joint Water District were being billed and how the town was getting reimbursed.

In response, Councilman Bianco said he didn't know that Yorktown supplied water to Cortlandt and that the town would look into the issue. Supervisor Peters also said that the town would look into the matter and explained that the town saves money by participating in the Joint Water Works with Cortlandt and Montrose.


September 2, 2008
During Courtesy of the Floor, Howard Frank, representing the United Taxpayers of Yorktown, reported that in response to his FOIL request he had received an “excellent” report from the Joint Water Works. But, he added, the report contained no numbers and didn't give an indication as to the efficiency of the plant. He urged board members to look into this matter. He also asked the board to check into the condition of some of the water meters being used in Cortlandt.

In response to Mr. Frank's comments, Eric DiBartolo, Director of Labor Operations noted that Mr. Frank had raised some good points but that the meters being used in Cortlandt were “radio read” (a passing car reads the meters) and were doing a good job. He added that the Water Department has an ongoing program to check the condition of meters.


September 16, 2008
Director of Labor Relations Eric DiBartolo reported that he had recouped $204,000 in water charges for 33,000,000 gallons of water that had been used over a number of years but which had not been paid for. He distributed a sheet with the names of the users and the amounts owed. The list included the Highway Department which he said had not been billed for the water it had used. He noted that five bosses before him had not been able to address the problem and he commended the staff in the Water Department for their hard work.

He also noted that New York City has announced an increase in water rates but that he was hoping that the 2009 budget for the Water District might be able to show a tax decrease because of savings he has been able to make.


September 23, 2008, work session
Request for water refund

A resident who had received a water bill for 72,000 gallons of water (during a time when no one was living in the house for several weeks) when her normal bills over several years were for 9,000-13,000 gallons asked the board the install a new meter. She said that the water department had inspected her house for leaks and found none and said that there was no problem with the existing meter. She also had a letter from a plumber who checked the house for leaks and found none.

Mr. DiBartolo said he would have a new meter installed the next day. If the high usage continued, he said then the problem would likely be on the “house” side of the meter and that the homeowner would have to look further into the source of the problem.

The homeowner has paid the bill for the 72,000 gallons to the Joint Water Works but said she hoped she would get a credit on future bills if it was found that there was a problem with the original meter.


October 7, 2008
The owners of the Pied Piper Nursery School complained about a recent North County News article that listed them as one of the town business that had been “stealing” water from the town. Concerned about their reputation, they explained that there had been a problem with the water meter that the town had installed at their facility and that the town had corrected the problem. The facility was on a list of businesses with meter problems that resulted in their not paying for the water they consumed.

In response, Director of Labor Operations Eric DiBartolo noted that he had never said that the preschool stole water and he acknowledged problems with the meter. Councilman Campisi also noted that it was not the town who used the word “steal.”


October 28, 2008, work session
Water Department: Proposed new laws
Director of Labor Operations Eric DiBartolo proposed the following new laws that are designed to raise revenue to help offset the 12% increase in water rates that New York City charges the Joint Water Works. The Water Works will absorb 3% of the increase and pass the remaining 9% on to Yorktown rate payers.

1. Raising the price of bulk usage (used by construction companies) to $15/gallon from $13/gallon.

2. Increasing out of district water charges

3. Adding a new section to the existing water ordinance that will charge commercial properties, condominiums and town houses a $350 service fee if a water department employee has to come to the site evenings or weekends to shut off the water for non emergency reasons. No fee will be charged during those hours for emergency shut offs. The law currently provides for a $25 fee for shut offs.

4. Setting the rate the town pays for water at cost, as distinct from the rate homeowners pay. Mr. DiBartolo advised the board that many town facilities are currently unmetered despite their using considerable amounts of water. This situation is in the process of being changed so that the town will get billed for the water that is uses.

In a separate water department issue, Mr. DiBartolo briefly informed the board that the 2009 water department budget will include a $60,000 expense for replacing 30 outdated hydrants. The department needs to replace a total of 120 hydrants and will complete the job over a period of years.

December 2, 2008
A series of four separate public hearings were held on local laws dealing with water rates and charges for the services of the water department. See October 28, 2008 meeting notes for a summary of each law. There was no discussion or public input and each law was passed unanimously.


February 17, 2009
Backflow inspections

Director of Labor Operations Eric DiBartolo advised the board and the community that the Water Department was in the process of sending out about 200 letters to businesses and condo complexes advising them that the town would be conducting “backflow inspections” in the coming weeks. He said that the inspections had not been done since 2000. The inspections do not apply to residential dwellings.


March 3, 2009
Water Department Water Usage
During Courtesy of the Floor, Director of Labor Relations Eric DiBartolo reported that in 2008, the department was able to reduce the town's water loss by 16%, down from 21% in 2007. He said he was still striving for a 10% loss goal for 2009.


Water Department: Other Issues (See also Miscellaneous Issues below)


June 2, 2009
Water rate increase
Howard Frank informed the board of the pending decision by New York City to increase the rate it charges for water. He said that while Director of Labor Operations Eric DiBartolo had done a good job in eliminating water loss (water usage that was not being paid for), he felt that more could be done at the treatment plant to reduce water usage relating to cleaning filters.

In response, the board passed a resolution opposing the proposed rate increase. Supervisor Peters noted that in the past, the water district has absorbed all or some of the increases in rates so that property owners had to pay only a portion of some of the increases.


July 14, 2009, work session
Changes in town water code
Director of Labor Operations Eric DiBartolo advised the board that he would be working with the town attorney on the last phase of amendments to the town's water code.

One change will require double meters in situations where there is a bypass installed on a large pipe. At present, water can be diverted by means of a bypass in such a way that it is not metered.

A second change will tighten up the requirements dealing with back flows and a third change will set a fee when the town's water department performs certain services on private property.

The changes will all be subject to a future public hearing.


September 1, 2009
A public hearing was held on proposed changes in the water code as previously discussed at the board's July 14, 2009 work session.

The only non town employee who spoke at the hearing was Howard Frank but because of audio problems, his comments were not audible to the audience. Responding to Mr. Frank's comments, Director of Labor Operations Eric DiBartolo explained that the new charges being proposed were designed to cover cost, not make money.


May 25, 2010, work session

1.      Maintenance Material Bid - Comprehensive package for all vendors with AWWA Standards to complete to bid on materials.

2.      Leak Detection Survey -- $19,000 was lowest bid for 174 miles of water lines.  Possible leaks up to 250,000 gallons cumulative

3.      Status of 5 Bay Garage - originally built as joint venture for highway department and water department vehicles.  Water Dept wants to store their newer vehicles.  A meeting between Eric DeBartolo and David Rambo with board members to work out storage arrangements.


Miscellaneous Issues (staff allocation, highway department, parks, YCC, etc.)


For other YCC issues, see
YCC page

Flexible use of labor staff
1/8/2008 (work session)
During discussion of tree removal at the Downing Park commuter lot, DiBartolo told the board that he had had used parks, water, and environmental conservation laborers interchangeably on a few projects; Parks people helped turn some water valves and water, parks and environmental conservation worked at park site. Bianco reminded him that he has to be careful about properly accounting for water department staff as it's a special district. DiBartolo said he was being careful to do that.


1/22/2008 (work session)
Mr. DiBartolo reported the following projects had been begun and/or completed:

·  He has developed a maintenance plan for Town Hall's bathrooms with an hourly checklist for each bathroom.

·  Swimming Pools: He had a "long" meeting with Recreation Commission regarding maintenance/repair issues at the pools. He is drawing up specs for the work to be done by an outside contractor.

·  YCC: Some unspecified drainage work was done.

·  Outdoor lighting: He is reviewing the need for outdoor lights at some of town's facilities. He is currently planning to install lights at the Shrub Oak pool which is dark and has been subject to vandalism. No costs were discussed.


April 1, 2008: Report on overtime
Mr. DiBartolo announced that for the first quarter ending March 31st, combining the labor services of several departments had reduced overtime costs to $17,800, compared with $64,000 for the same period in 2007. He asked to meet with the board in a work session to provide a fuller report.

Personnel
The board approved a resolution approving the stipend for the Deputy Highway Superintendent that was discussed during the 2008 budget hearing. There was no discussion on the resolution or mention of the amount of the stipend.


April 8, 2008 (Work Session): Quarterly report
Director of Labor Operations Eric DiBartolo, accompanied by Patrick Lofaro, head of the Department of Environmental Conservation and the Deputy Highway Superintent gave the board a quarterly update on projects undertaken by the combined labor forces of the Parks, Water, Highway, Environmental Conservation and Sewer Departments.

75 projects have been completed including

·  getting the town's ballfields ready three weeks earlier than last year

·  improvements to the Hunterbrook soccer field

·  improvements to the London Woods fields

·  completion of new parking lot adjacent to the high school

·  lowering the level of Sparkle Lake (see below)

·  demolition of old Parks & Rec office building at Sparkle Lake

·  swimming pools have been sandblasted and are ready for painting

Mr. DiBartolo also said that the town had saved $80,000 on the new boiler for the YCC by changing the installation date and that $45,573 had been saved on overtime, mostly in the Water Dept, and not including any snow related overtime.

In the Water Department he has instituted a value turning program that should reduce water loss and is going after non payment of water bills. He mentioned one business that has not paid a bill in 10 years; the total was $20,800. The department is also metering water sales to businesses that fill up at hydrants for spraying.

His goal is to reduce water loss, which he estimated at 14% and called "way out of control," to 5-6%. He can accomplish this, in part, with new software that allows him to shut off specific lines once a leak is discovered.

On the Legacy Ballfields, he told the board that this would be the highest priority for all the departments under his control in the coming weeks. He could not estimate how long the job would take (the town has the responsibility for cutting the trees and preparing the site; an outside firm will do the final "finishing" for the fields.) as the DEC and DEP will only allow the town to disturb 3.3 acres at a time; as each area is stabilized, crews will move on to the next area.

Mr. DiBartolo is investigating purchasing a used "roller" for use in preparing the fields. The roller would be sold when the job is finished. He estimates that renting a roller for four months would cost $20,000-$30,000 but that he could get a used roller for $12,000-$18,000 which he could then sell.

Blacktop: Because the price has risen from $60.20 to $89.90 a ton from 2007 to 2008, the highway department will only be able to pave 3-4 miles of road this coming season.

Sparkle Lake: Mr. DiBartolo has obtained a wetland's permit to lower the level of the lake (which has already been done) although he said that town engineer Sharon Robinson said that one wasn't needed. He told the board that neither Mohegan Lake or Shrub Oak Lake get wetland's permits when they are lowered.

He defended his plans for the revitalization of the lake in the face of being "beaten up on" and that one or two people didn't like the plans. He said that if the fish didn't like the blue fiber optic light on the fountain, he would shut off the light. He didn't think the light would alter the ecology of the lake. He also stated that the lake was looking "great" after having lowered the water level.

He explained that the aerator/fountain would not involve any digging of trenches (the hose would drop into the water where the current cage is located) and that therefore no wetland's permit would be needed for that activity. He said that an aerator/fountain would be better than a simple aerator. Councilman Bianco stated that as long as the fountain didn't require any electric cable in the lake, no permit was needed.

Councilman Metz said he had received inquires from homeowners in the Junior Lake area wanting to know if Mr. DiBartolo could initiate similar type improvements for Junior Lake.

Councilman Bianco asked Mr. DiBartolo to copy the board on his projects as he does for highway department projects. Mr. DiBartolo said he appreciated the trust the board had in him.


July 15, 2008
French Hill Pump Station

The board authorized the supervisor to sign an agreement for the design of the French Hill Pump Station Rehabilitation Project.



August 5, 2008
Sparkle Lake:   Eric DiBartolo, Director of Labor Operations stated that he wanted to correct the record on two issues dealing with the town work force. He noted that despite the criticism he had taken about the renovation of Sparkle Lake, the lake was in very good condition and that he had received many letters thanking him for the improvements he had made. He said that he was looking in to rehabilitating Crystal Lake next year.

Vactor machine:  Mr. DiBartolo also said that the vactor machine that had been purchased by the Water Department for $284,725 but which could not be used because it had been incorrectly speced would be returned to the vendor for a 4% restocking fee that would cost the town $11,360. He is currently checking with other towns before drawing up new specs and purchasing a new machine.


August 19, 2008
Although on the agenda, Councilman Campisi said he thought that the board wasn't ready to advertise for bids for the a new sewer vaccum truck, to which Town Clerk Alice Roker responded, “trust me, it's okay” without adding any explanation.

In response to a question during the second Courtesy of the Floor as to what the unspoken issue was about, Ms. Roker said she had had a discussion with the town comptroller and there was some question about the disposition of the existing vactor truck that the town had tried to sell at auction but for which it received no bids. She did not elaborate. She explained that if the board voted to authorize her to advertise for bids, she would not proceed with the advertising until the board was ready to proceed with the purchase. The board gave her the authorization.


September 23, 2008, work session: Update on combined operations
Director of Labor Operations Eric DiBartolo and Pat Lafero, head of the town's Department of Environmental Conservation, gave a third quarter update to the town. A copy of the full report is available in the town clerk's office.

Mr. DiBartolo reported that five budgeted position have not been filled and will not be included in his 2009 budget request, resulting in a $365,000 savings. He said that overtime in 2008 from Jan-Sept had been reduced by about $95,000. He attributed the savings to the ability to combine the labor of several departments. Overtime in the water department was down but up in the highway department due to the illness of one worker who had to be replaced by a higher salaried person. In general he said that town staff was “doing more with less.”

Mr. DiBartolo also explained that he had notified condominium owners that the town would charge a $350 fee if water department services were needed over the weekend for non emergency calls.

He also suggested that the town try to add Sunday flextime to the CSEA contract.

He is also planning to centralize all town purchasing in the town's central garage, although Town Clerk Alice Roker noted that the Yorktown school district was interested in working with the town on joint purchases and that this issue needed to be discussed further.

Councilman Metz noted that he had gotten lots of compliments about Sparkle Lake (Mr. DiBartolo said the iimprovements cost under $10,000) and requests from residents of the Junior Lake who wanted similar improvements be made there. Mr. Di Bartolo said he was planning to cut shrubs and aerate Junior Lake at a possible cost of only $2,00-$3,000 as there was no swimming in the lake and as long as his plan didn't present any problems with the town's insurance carrier. He said that improving Crystal Lake would be more difficult as there wasn't as much town owned land surrounding it as Junior Lake.

Ms. Roker asked if there was any correlation between the aerators in Sparkle lake and the absence of geese in the water. Mr. DiBartolo said he didn't know but would look into it.

YCCC: Mr. Lafaro reported that the new boiler has been installed in the YCCC and that it will use between 8-9 gallons/hr compared to the older boiler that used 22 gallons/hr.

In response to a question from Mr. Roker about the status of fire code violations in the building that dated back to the early 1990s, Mr. DiBartolo reported that they had all been corrected except that some work remained to be done on the sprinkler system in the auditorium (he was waiting for a plumber to hook up a pipe that had been installed.) He explained that the new, less expensive system, would create a water curtain spray between the stage and the rest of the auditorium and would be $60,000-$75,000 less than other options. The new alarm system has been installed and is functioning and improperly stored materials have been removed.

Legacy Field: Mr. DiBartolo reported that work had began on the entrance road. If the current work cannot complete the covering of the gas line by November 1st, additional work on the project will have to wait until next year. In a separate action, the board awarded a contract for $131,000 to remove the trees and stumps from the site. (A second bid came in at $252,000.) How the trees would be disposed of what not explained.


March 24, 2009, work session
New Department of Environmental Conservation fees

On the recommendation of Director of Labor Operations Eric DiBartolo, the board voted to increase the following costs and bring them more into line with the town's actual costs. The new costs will go into effect immediately.

a. leaf bags, which cost the town 29 cents a bag and currently sell for 25 cents will be increased to 30 cents. (Mr. DiBartolo initially suggested a 50 cent charge.

b. The cost of recycling bins will be increased to $6.00 from $5.47.

c. The cost of a special bulk pickup will be increased to $35 from $25. The rate hasn't been changed since 1983. Mr. DiBartolo explained that it is not possible to charge based on the amount collected and that only a flat rate was workable. He initially suggested a $50 fee which the board felt was too high.

Change to bio diesel fuel
Director of Labor Operations Eric DiBartolo advised the board that as part of the town's commitment to be “more green” he will be switching to bio diesel fuel which will cost 4 centers more per gallon but also cut fumes.


April 7, 2009
Town vehicles

During Courtesy of the Floor, Steve Gardner called attention to the fact that some town trucks and vehicles did not have adequate safety lights on them and that slow moving vehicles did not have the required triangular signs. He said both were needed for safety reasons and suggested the that the town comply with federal and state regulations.

In response Highway Superintendent Eric DiBartolo defended the safety record of his department and his record since taking office in 1995.


Highway Department Vehicles
April 21, 2009

Citing documents relating to the inventory of vehicles and equipment in the highway department that he had obtained as a result of a Freedom of Information request, and which he said were incomplete and “like swiss cheese,” Steve Gardner called attention to the fact that in the 12 years that Eric DiBartolo has been highway superintendent, the town has spent $134,000 on four, or possibly five cars, for the superintendent's personal use, or about $40,000 every three years. He compared that expense to the types of cars that previous highway superintendents had used.

In a second courtesy of the floor, he said that in the past 11-12 years, the number of vehiccles in the department had doubled from 32 to 80. He raised the issue of the cost of maintaining and operating these vehicles, suggesting that it might be more cost effective to contract out some services, such as snow plowing, tree work, drainage and paving as was done in the past. He said he had been told that the $245,000 paving machine the town bought 10 years ago was broken down and was stored uncovered outside during the winter months, jeopardizing its delicate machinery.


April 29, 2009, work session
Park issue
Although not on the agenda, there was a brief discussion about a disagreement between Mr. DiBartolo and another town employee over who had jurisdiction to change some locks at an unnamed town park facility. Mr. DiBartolo said the locks had been changed as a common sense measure that would save the town money. Councilman Campisi advised him, however, that changing the locks was not a maintenance issue and that it was not an issue for Mr. DiBartolo be worry about.


May 5, 2009
Highway Department issues
Steve Gardener maintained that Yorktown is not providing its highway workers with safety equipment up to NYSDOT standards.  This equipment includes lights and placards on equipment and safety equipment for workers.  He cited worker health and safety issues and potential Town liability.  As part of his presentation, Mr. Gardener provided the Town Board members with photocopies of a Journal News front page photo showing Yorktown Highway Department workers working filling potholes without appropriate safety gear.  He also donned a reflective vest and hard hat for his presentation.
 
Mr. DiBartolo responded to criticism leveled by Mr. Gardener at previous Town Board meeting during courtesy of the floor.  He said that prior to 1996 the Town's dependence on private plowing and tree services had been very costly with poor accountability. Having this work done by Town employees with Town equipment, as is now the case, provides better service more economically.  Mr. DiBartolo pointed out that all his predecessors drove Town vehicles, but he requires a large truck because he actually uses it for snowplowing and carrying equipment such as chain saws.  Mr. DiBartolo also said he found it strange that Mr. Gardener had money for props used in his courtesy of the floor presentation, but not to pay outstanding taxes.  He wondered how someone who could not manage personal finances could hope to manage the Highway Department's $5 million budget.
 
At the second courtesy of the floor, Mr. Gardener said he fell behind in his property taxes during a time period when his parents were ill  and caring for them was his first priority.


Library roof
April 22, 2008 work session
Director of Labor Operations Eric DiBartolo advised the board that bids for the new library roof had come in at $242,000. (The bid will be awarded at the May 6th public meeting but he wanted to give the board a "heads up" so that work could begin ASAP.) He explained that $70,000 of the cost will come from a grant the library obtained through Senator Liebell; the remaining funds will come from the $5M bond authorization the town approved earlier. Councilman Bianco noted that the project had not been included in the earlier plans for the bond issue but Councilman Campisi said that since the town had saved money on other capital projects funded with the $5M, there would be funds to finance the unplanned for roof expense. (Note: to date, only a portion of the $5M has been borrowed or committed.)

May 6, 2008
The board unanimously approved a bond authorization for $100,000 to pay for a portion of a new roof at the library. The total cost of the project will be $252,727, with $70,000 coming from a grant that Senator Liebell previously had obtained for the library. Mr. Bianco asked where the additional $80,000 would come from and told Mr. DiBartolo that he would appreciate getting the paperwork on this type of expense prior to the meeting. Mr. Campisi thought the additional funds might be in the 2008 library budget but no one was sure. Mr. DiBartolo said that town comptroller Joan Goldberg would email the board the next day with the details of the financing. The bid was awarded. The new roof is expected to last for 30 years.


September 22, 2009 work session
Security gate at rear of police station

At the request of Director of Labor Operations Eric DiBartolo, the board agreed to erect a gate at the rear of the police station to secure gas pumps used by town vehicles. The gate will be closed during off hours and a key will be in the police station. He explained that this location was the only one with gas pumps that was wide open. Her added that the gate will only be an inconvenience for employees needing to fill up during “weird hours.” The gate will remain open on Tue and Thur evenings when court is in session as prisoners are brought in from a rear entrance.


Shrub Oak Swimming Pool
April 22, 2008 work session
In a brief discussion, Director of Labor Operations Eric DiBartolo advised the board that an additional work had to be done on the pool before it will be ready for use. The town had planned to cement and paint the pool surface after it had been sandblasted, but the Westchester County Department of Health said that the pool surface had to be retiled, not painted. No cost for the additional work was discussed. The project will be advertised for bids at the May 6th meeting. The board is anxious to have the pool ready by the beginning of the swimming season.


Central Garage
May 6, 2008
Mr. DiBartolo announced that in the next few days the central garage located behind the Police Building would relocate to the Highway Department building and that all town vehicles would now be repaired at that site. Mechanics who previously worked for the Water Department, the Central Garage and the Highway Department would now all be located in the same facility.

Initially, the plan was to relocate the central garage to the Water Department building in Shrub Oak but the needed renovations proved too costly. Under the new plan, the Highway Department will store some of its vehicles in the Water Department garage.

Wood chips for playgrounds
May 6, 2008
Wood chips prepared by the town will now be used for the town's playgrounds, replacing chips that were previously purchased from other vendors (and the town prepared chips sold to other vendors). Mr. Di Bartolo reported that the chips had been tested by a outside firm for its compaction properties and that the town “now has a permit to use the chips for the next five years.” He did not say who issued the permit.


Energy Conservation

May 20, 2008

During the Courtesy of the Floor portion of the meeting, Director of Labor Operations Eric DiBartolo provided the board with the following updates.
a. Energy efficient vehicles. He has put a hold on his earlier plans to purchase energy efficient “smart cars” while he is looking into some negative reports about them. Councilman Bianco noted that he had advised Mr. DiBartolo that one problem with the cars was that they required hi-test gasoline which would make them more expensive to operate. Mr. DiBartolo also plans to purchase some 3-wheel vehicles (possibly known as “cushmans”) for use by town employees for running errands in and about town. Memos have also gone out to town employees that when using town vehicles, they should not let cars idle more than 3 minutes. In response to Councilman Metz's question about the feasibility of using ethanol, Mr. DiBartolo said that there were currently problems associated with their use in town vehicles.

b. Mr. DiBartolo advised the board that diesel fuel has increased in cost from $1.52/9/per gallon in 2007 to $3.79/9.

c. At the YCC, efforts are underway to reduce electric usage by installing automatic light switches and installing more energy efficient light bulbs.


Fleet Committee (Town Vehicles)


11/27/2007 (work session)
1. issue was whether to bring police cars into purview of existing committee.
2. Bianco felt police cars had different needs; maybe should be left to police to decide
3. DiBartolo said police chief was on committee
4. There had been past issue where chief has done things with old cars that might have been done differently if under purview of the committee
5. all agreed that chief has done a good job on getting very good price on new police cars
6. after chief walked in to discuss another issue, DiBartolo must have spoken to him as he later told board that chief had no problem with fleet committee dealing with police cars
7. as a result of fleet committee, town vehicles are now almost all same brands; very much unlike before when each department head could recommend his personal brand preference and town had to stock parts for different brands.
8. DiBartolo talked about how there would be a central garage


May 20, 2008
For a discussion about "smart cars" and 3-wheel "cushmans" see:
Energy Conservation


October 28, 2008, work session
Town Vehicle Repairs
Director of Labor Operations Eric DiBartolo requested the board adopt a policy statement that all town vehicle repairs will go through the Fleet Committee composed of Town Comptroller Joan Goldberg, Pat Lofaro, Environmental Conservation Superintendent, and himself.

The town's central garage was recently relocated from behind the police station to the highway garage. As vehicles come in for repair, they will be attended to according to a schedule and work will only stop on vehicles currently being repaired in the event of an emergency. Mr. DiBartolo also said that the town had an unexplained inventory of 500 tires and that from now on, departments would not be able to purchase tires on an “as needed” basis but would have to go through the central garage.

There was also a discussion questioning how many actual police cars there were (and were some being “hidden”) and the discovery last fall that in the water department some vehicles were “reserved” for use by only certain individuals.

Mr. DiBartolo said that by the first of the year, his office should have computerized records for all vehicles indicating their mileage, repair history, etc. The records for some departments are already computerized and the remaining ones are on paper and are being transferred to the comput.

The board will draft the policy statement for approval at a future board meeting.


See also Bids & Contracts for more information about the purchase of trucks, and Highway Department Vehicles for comments relating to the number of highway department vehicles.


July 28, 2009, work session
Drainage project on Underhill Ave.

This item was not on the agenda. The town expects $100,000 as a reimbursement for work done on the Route 118 turning lane. When the money is received, approximately $62,000 will be used to repair a drainage pipe along an easement on Underhill Avenue in the general vicinity of Meadows Farm and the bike path. Details of the project were not discussed.


August 11, 2009, work session
Emergency Culvert Repair/Underhill Ave.

The board authorized the emergency repair to clean and realign of a 36' culvert on Underhill Ave opposite Yorktown Glass that is on a town easement. Because the work is considered an emergency (Deputy Town Clerk Diana Quast said there were two memos on file regarding to issue and that there is a danger of a falling telephone pole), the work was not bid out. Green Mountain Pipeline Services was selected as the sole supplier of the type of pipe being used on the job and the highway department will do additional work on the site. The cost of the job was not disclosed, only the cost of the piping, at $276 per linear foot.


Fire Zone Regulations

Regulations governing stripping and signage in fire zones
July 28, 2009, work session

This item was not on the agenda and was brought up by Town Clerk Alice Roker.

The town court has thrown out some tickets for illegally parking in fire zones because the stripping lines were not clearly visible or the no parking signs were not present.

Ms. Roker gave the board copies of a letter from the NYS comptroller's office that included a copy of a 1987 state attorney general's opinion that it was the town's responsibility to see to it that the stripping was done and property maintained. Highway Superintendent Eric DiBartolo said that doing this in all the town's shopping centers would cost $17,000 a year. He also raised the issue of how the town could do something on private property.

It was decided that the town attorney would send a letter to shopping center owners reminding them of the stripping requirement but that the town would also consider adopting a local law making commercial property owners responsible for doing the stripping.

Return to Home Page