Hilltop Road
Location: Hilltop Road, Yorktown Heights
Description: Proposed 3 lot subdivision on 13.088 acres in the R1-40
zone
Section 37.06 Block 1 Lot 25
Represented by: Al Capellini = lawyer and
Jack Goldstein=engineer
1/14/08: Hilltop Associates: Decision Statement
The Planning Board declared itself the lead agency under SEQRA for this
project and then adopted a negative declaration of environmental impact,
i.e., the project will not have a significant negative impact on the
environment. The Planning Board adopted a resolution approving the
preliminary layout, subject to the applicant addressing the comments made in
the public hearing.
September 22, 2008
The board approved a 90 day extension while the applicant waits for Health
Department approval.
October 6, 2008
Request for 2nd 90 day time extension: The time extension, requested because
Board of Health testing is still in progress, was granted.
February 9, 2009
The board reapproved the preliminary subdivision
plan. Two of the plan's three lots have already received health department
okay for septic systems; the third lot needs to be retested and this cannot
be done until the weather improves
August 10, 2009
Rainy weather delayed DOH observation of perc
tests. The requested 1st 90 day extension was granted.
September 14, 2009
The board approved a second 90 day extension. The delay is getting Board
of Health approval.
The 3 lot subdivision was approved by Planning Board Resolution 08-02
on January 14, 2008.
December 14, 2009
According to
Mr. Capellini, the applicant had been waiting for
the Department of Health to witness the septic system perc
tests and deep-hole tests. Since the application has already had two 90 day
extensions, it had to be re-approved, which the Planning Board did.
|